Team portfolio

Tengiz process facilities

Engineering solutions for upgrades to process equipment and field infrastructure.

Tengiz process facilities
Client / participants
TCO
Location
Tengiz
Period
2014–2018

Equipment upgrades

Project X-600-008-14: corrosion-protection upgrades to air chambers on units 3 and 4. Technology vendor Enersul, Canada; TCO unit 600, replacement of GX3 and GX4 plenum equipment.

Pipelines and water systems

Reconnection of the export gas pipeline to the Central Asia–Centre 4 main at km 597; conversion of single-well site equipment from high to low pressure; new water-system buffer tanks; replacement of a high-pressure gas line and a sodium hypochlorite unit for revised treatment capacity.

Safety and infrastructure

Electronic security design package for warehouse 7 at Balkany and connection of a container laboratory to existing utilities. Further experience includes temporary container storage (2014–2015), the TCO training centre through Atyrau Tengiz Construction Service LLP (2014), replacement of substation TCO VNG-4300-049-16 through PSI ENERGY & CONTROL (2018) and logistics and warehouse offices through ATCS (2018–2019).